A New Multi-Use Games Area for a Community Sports Hub in Nottingham

Get in Touch

When a community sports hub in Nottingham contacted our team, they had an ambitious idea for an outdoor area that was not being used to its full potential.

The site consisted of an open section of land alongside the existing community facilities. Although the space was occasionally used for informal activities, it lacked a suitable playing surface, defined court markings and secure perimeter fencing.

The organisation wanted to create a Multi-Use Games Area (MUGA) that could accommodate several sports while providing a dedicated facility for local clubs, youth groups and recreational sessions.

Our involvement began with a meeting between our project team and the people responsible for managing the sports hub.

They explained that the new court needed to be versatile enough for football, basketball and netball, while remaining practical to maintain.

After discussing the available options, we proposed a new macadam MUGA with a specialist sports coating, contrasting line markings and perimeter ball-stop fencing.

The proposed construction would provide a suitable foundation for the intended activities while allowing the organisation to manage different sporting sessions throughout the week.

Planning the Project Around Community Needs

One of the first questions the client asked was whether the court could accommodate several activities without requiring equipment to be moved constantly.

We discussed the proposed court layout, the positioning of basketball hoops and the options for football and netball equipment.

The sports hub also wanted the facility to feel welcoming rather than resemble a plain tarmac enclosure.

We suggested a coloured sports coating with a green playing area and contrasting blue sections, along with different coloured markings to identify the relevant sports.

During the planning stage, we also reviewed site access, drainage requirements and the proposed location of the fencing.

The client was particularly concerned about balls leaving the playing area and affecting nearby outdoor activities.

To address this, we included a suitable perimeter fencing arrangement in the proposed design, with access gates positioned to support safe entry and maintenance.

Once the specification and layout had been agreed, we prepared a construction programme of approximately five weeks, subject to ground conditions and suitable weather.

Establishing the Site and Starting Groundworks

The first week focused on preparing the area for construction.

We established the working zone, organised material deliveries and carried out the necessary setting-out work.

Our team then began excavating the existing ground to the required formation level.

This stage involved removing unsuitable material and preparing the area for the new sub-base construction.

We also checked the existing ground conditions to confirm that the proposed build-up remained appropriate.

Because the site was being developed from an informal outdoor area into a dedicated sports facility, getting the levels and drainage right was especially important.

The court needed a suitable construction that would support regular use and help prevent water accumulating on the playing surface.

Building the Foundation and Drainage System

During the second week, our team progressed with the drainage and sub-base installation.

We installed the specified drainage components and prepared the formation for the engineered aggregate layers.

The sub-base was placed and compacted in accordance with the project specification, with levels checked throughout the process.

This work provided the foundation for the new macadam sports surface.

One of the community representatives visited the site during this stage and asked why so much of the programme was dedicated to work that would eventually be covered.

We explained that the quality of the underlying construction plays a major role in the long-term performance of an outdoor sports court.

An attractive surface alone cannot compensate for poor drainage, inadequate compaction or unsuitable base preparation.

The client appreciated the explanation and was pleased to see the project progressing.

Installing the Macadam MUGA Surface

By the third week, the site was ready for the sports macadam installation.

The selected macadam system was laid in accordance with the agreed specification, with the appropriate layers compacted to create a consistent playing surface.

Our installers carefully checked the finished levels and transitions around the perimeter.

Particular attention was given to the areas around the proposed fencing and equipment positions.

Once the macadam works were complete, we allowed the surface to become suitable for the next stage in accordance with the coating system requirements.

This was an important part of the programme, as applying a sports coating before the substrate was ready could affect adhesion and the quality of the finished surface.

Adding Colour, Court Markings and Fencing

The fourth week was when the project began to take on the appearance of a completed sports facility.

Our team applied the specialist sports coating, creating the agreed green and blue colour scheme.

After the necessary drying intervals, we set out the court markings for the different sports.

The markings were applied in contrasting colours to make the individual layouts easier to distinguish.

Meanwhile, the perimeter fencing installation was completed, including the access gates and associated fittings.

The fencing helped define the playing area and provided ball containment for the intended activities.

We also coordinated the installation of the agreed sports equipment, ensuring that the positions were consistent with the court layout.

When the sports hub representatives returned to review progress, they commented that the area was beginning to feel like a genuine community facility rather than an unused piece of land.

Final Inspections and Handover

The fifth week was allocated to completing the remaining details, carrying out inspections and preparing the MUGA for handover.

We checked the condition of the finished sports surface, reviewed the line markings and inspected the fencing and equipment installations.

We also discussed routine maintenance with the client.

For a macadam MUGA with a specialist coating, this includes keeping the court free from debris, cleaning the surface using suitable methods and checking for damage or drainage problems.

The client was also advised to follow the relevant manufacturer's recommendations for the installed system.

The full construction programme took approximately five weeks, including groundworks, drainage, surfacing, fencing, equipment installation and final inspections.

The court was opened for use only after the required coating curing period and completion checks.

A New Opportunity for Local Sport

The completed MUGA provided the Nottingham community sports hub with a dedicated outdoor court suitable for its planned range of activities.

Instead of an informal open area, the organisation now had a clearly defined sports facility with a constructed playing surface, multi-sport markings and perimeter fencing.

The client was particularly pleased that the court could support different sessions without requiring separate playing areas for each sport.

For our team, the most satisfying part of the project was knowing that the new facility could help the organisation expand its activities and make better use of its available outdoor space.

It was a project that demonstrated the value of careful planning, appropriate groundworks and a sports surface specification selected around the needs of the people using it.

Planning a New MUGA for Your Community?

We help community organisations, schools, leisure centres and sports clubs explore Multi-Use Games Area construction, resurfacing and refurbishment projects across the UK.

Whether you're developing an unused outdoor space or replacing an ageing sports court, our team can discuss suitable surfaces, drainage, fencing, line markings and installation requirements.

Contact us today to request a quotation and find out how we can help bring your next MUGA project to life.

Get in Touch

We aim to get back to you in 1 working day.


Skip to

Privacy Information

Social Links